Victoria Orders Western Renewables Link Cost Review, Pauses Compulsory Acquisitions

The State of Israelでこの記事を読む

Courtroom-sketch editorial illustration of electricity transmission supports and conductors from a May 2010 photograph; archival energy-infrastructure context, not the project, local equipment, outage or storm reported.
AI courtroom sketch of electricity transmission supports and conductors from a May 2010 photograph; archival energy-infrastructure context, not the project, local equipment, outage or storm reported. Adapted from the credited reference. Anchor pylon of high-voltage overhead power line 750 kV.jpgNovoklimov; CC0.

Victorian Premier Ben Carroll has ordered an immediate, independent assessment of the Western Renewables Link’s costs, with findings due to be published by the end of 2026. The government said no compulsory acquisitions will occur during the review. The proposed 190-kilometre transmission line from Bulgana to Sydenham is now estimated at A$1.5 billion, more than three times its 2019 estimate, and its environmental-effects statement was approved on Tuesday. The project still requires state and Commonwealth agency approvals and parliamentary approval, while planning officials found significant visual and landscape impacts could be managed through mitigation.

出典

一次資料:1二次資料:2

関連記事

  1. ハバナ、全国送電網の切断後に顧客の45.6%への電力供給を復旧
  2. Adani Airports Signs $1 Billion Equity Deal With Global Investors
  3. India Completes 2,800-Kilometre Dedicated Freight Corridor
  4. Three International Groups Apply to Build Bogotá Metro Line 2
  5. Nigeria’s Defence Minister Says ₦5.41tn Budget Covers Weapons and Troop Pay

問題が発生しました

操作を完了できませんでした。接続を確認して、もう一度お試しください。